Requirements specification and functional specification: what does a web project need?

Many projects are delayed because they wait for a complete document that nobody can write. This text explains the terms, names the cases in which they are really needed, and says what is enough otherwise.

  • Who it is forManagement, project managers, purchasing
  • LevelProject planning
  • Reading timeabout 7 minutes
  • Last updated16 October 2026

What you will learn

  • What the Lastenheft (requirements specification) and the Pflichtenheft (functional specification) each are
  • When the effort pays off — and when it does harm
  • Which six details are enough for a reliable start
  • How to deal with what you do not yet know

Two documents, two authors

The Lastenheft (requirements specification) describes what the client needs: the task, the constraints, the goals. It is written by you, in your language.

The Pflichtenheft (functional specification) describes how the contractor intends to implement it: solution approach, technology, scope boundaries. It is created at the developer, based on the Lastenheft, and is accepted by you.

In practice, this clean separation occurs mainly in public tenders and in regulated sectors. In a mid-sized web project, a single shared document usually emerges — and that is not a shortcoming but appropriate.

When the effort pays off

An elaborate requirements specification pays off if at least one of these points applies:

  • You are collecting quotes from several providers and want to be able to compare them.
  • Several departments have to agree on the same state of affairs before anything is built.
  • Regulatory requirements apply that must demonstrably be met.
  • The project is large enough that a misunderstanding costs months.

Where none of this applies, an extensive document can even do harm: it ties up weeks, becomes outdated during implementation and creates the illusion that everything has been settled. The important questions arise anyway once you see the first screens.

Six details that are enough to start

  • The process in your own words, step by step — the real one, not the ideal one.
  • Who works with the software and who makes which decisions.
  • Which systems are involved, including spreadsheets and mailboxes.
  • What should happen to existing data.
  • What explicitly is not part of it.
  • How you would recognise after six months that it was worth it.

The fifth point is almost always forgotten and is the most valuable. It prevents the discussion after acceptance in which both sides are right.

An example from practice

What you do not yet know belongs in it anyway

No requirements specification is complete, and that is fine — as long as the gaps are named. A sentence such as "How cancelled orders are handled in the annual report is still open" is worth more than a seemingly complete document that glosses over this question.

A developer who sees a named gap plans a decision for it. An unnamed gap is silently filled with an assumption — and assumptions come to light at acceptance, not before.

Common misconceptions

For a reliable estimate, the six details above are enough. A fixed price for an unclear scope would only be a priced-in risk anyway.

Detail in the right place helps. Detail about things that are clarified during implementation anyway ties up time and is not maintained later.

It is a description of the solution approach. What applies contractually is governed by the contract — the description can be referred to there.

About the author

Fabian Lücker is the managing partner of PHP-Schmiede KG in Rheine and has worked in software development since 2007. He is responsible for development and concept design, and here he writes about decisions that arise in real projects.